Project Overview
Con-Fused were the electrical contractors for a new extension at Judds Folly Hotel in Faversham, Kent. The on-site works included stripping out and rewiring all the power and lighting in the existing bar area and renovating it with new electrical lighting and wiring.
The works also included the fitting of a new fire alarm system together with emergency lighting and a new installation of power and lighting to the extension, including all electrical testing and certification.
Electrical Installation Works
- Electrical Rewiring
- Lighting
- Emergency Lighting
- Fire Alarm System
- Testing and Commissioning
The program took 6 weeks from start to finish.